Gas-Fired Power Plant Optimization (MILP)

This repository contains a mixed-integer linear programming (MILP) model for optimizing the operating schedule of a gas-fired power plant under operational constraints and uncertain future prices.


Problem Description

We model a gas-fired power plant operating in the period December 31, 2021 – February 1, 2022, after which the unit enters a long-term maintenance outage.

Given multiple simulated forward price scenarios for:

  • Power (€/MWh)
  • Gas (€/MWh)
  • CO₂ (€/ton)

the objective is to maximize total profit while respecting strict operational constraints, including:

  • Limited number of starts
  • Limited total running hours
  • Minimum and maximum generation levels
  • Start-up costs and energy consumption depending on downtime duration

Key Technical Parameters

  • Maximum capacity: 400 MW
  • Minimum stable generation: 220 MW
  • Remaining starts available: 15
  • Remaining running hours available: 250
  • Initial condition: plant is running at the beginning of the horizon

Start-up Types

Start-up behaviour and resource consumption depend on the number of hours the unit has been offline:

Hours offline Start Type Power produced during start (MWh) Gas consumed during start (MWh) CO₂ emitted during start (t)
≤ 10 Type 1 75 190 35
11 – 35 Type 2 190 700 130
> 35 Type 3 210 800 150

Start-up energy, gas and CO₂ emissions are accounted for in the hour before the unit reaches minimum stable generation.


Model Overview

The problem is formulated as a Mixed-Integer Linear Program (MILP) and solved using PuLP + CBC solver.

Main Decision Variables

  • is_on[t] – binary: plant is producing power in hour t
  • start[t] – binary: plant starts in hour t
  • start_type_1[t], start_type_2[t], start_type_3[t] – mutually exclusive start type indicators
  • gen_above_min[t] – continuous: generation above minimum stable level (MW)
  • consecutive_off_hours[t] – auxiliary variable for tracking downtime

Objective Function

Maximize total profit over the horizon:

Profit = Power revenue − Gas cost − CO₂ cost

Revenue and cost terms include:

  • Hourly generation revenue (including start-up power if credited)
  • Start-up fuel and CO₂ costs
  • Running fuel and CO₂ costs

About

MILP optimization model for a gas-fired power plant — maximizes profit under start-up constraints, limited starts/hours, and uncertain power/gas/CO₂ prices using PuLP + CBC.

Topics

Resources

Stars

Watchers

Forks

Releases

No releases published

Packages

 
 
 

Contributors

Languages